This guide provides step-by-step instructions on how to manage post-contract activities using C-Link.
Estimated Read Time: 3 Minutes ⏱
Before proceeding with this guide, you should familiarise yourself with the Post-Contract Management section.
Sections in this Article:
💼 Navigating Post-Contract Tools
📄 Creating and Managing Instructions
📊 Tracking Variations and Final Account Forecast
🎥 Full Walkthrough Video
💼 Navigating Post-Contract Tools
To begin managing post-contract activities for your project, follow these steps:
- Log into C-Link:
- Navigate to your C-Link dashboard.
- Access Your Specific Project:
- Select the project you wish to manage, for example, Gate Apartments.
- On the project dashboard, you will notice tools are divided into two categories:
- Procurement Phases: These include the project plan, procurement tools, and project documents.
- Post-Contract Tools: Includes Instructions and Variations, NCRs (Non-Conformance Reports), and Forecast Final Account.
📄 Creating and Managing Instructions
To create and manage instructions within your project, proceed as follows:
- Access Instructions and Variations:
- Click on the Instructions and Variations section under Post-Contract Tools.
- Create a New Instruction:
- Press Add New Instruction.
- Select the relevant subcontractor from the list. These will be subcontractors with an existing contract.
- The system will automatically connect the instruction to the relevant package.
- Enter a description of the instruction, for example, "Add a new room to the east elevation" or "Additional muck away required – 2 loads."
- Input the agreed rate from the contract, such as £400 per load, or leave it to be valued at a future date.
- Upload any relevant files or documentation to support the instruction.
- Save and Send the Instruction:
- Once the details are entered, you can save the instructions as a draft or preview them to see how they will appear as a PDF.
- Press Save and Send Instruction to issue it to the subcontractor.
- The system will then log the instruction in the Instructions and Variations tab, which shows all instructions with their respective dates and statuses.
📊 Tracking Variations and Final Account Forecast
To track variations and manage the final account:
- Track Instructions and Variations:
- After sending an instruction, it will appear in the Instructions and Variations tab.
- The tab will display all instructions sent for the project, including dates and recipient details.
- As agreements are made, the status of each instruction will be updated accordingly.
- Prepare for Future Updates:
- In future steps, you can manage NCRs and further track how these feed into your Forecast Final Account.
Summary ✅
This guide has outlined the process for managing post-contract activities in C-Link, including creating and managing instructions, tracking variations, and preparing for final account forecasting. By following these steps, you can efficiently manage your project's financial and operational aspects post-contract.